by hfdesigners | May 30, 2025 | Second Floor Addition
Month 6 Update This is our last video update before the final reveal! It’s been 6 months since we started this massive project in Azle, and we are down to the finishing touches. The exterior is finished and painted. The concrete floors downstairs are prepped for tile,...
by hfdesigners | May 5, 2025 | New Posts, Second Floor Addition
Month 3 Update It’s been a while since our last update, but we’re going into our 3rd month and things are moving along. This is still the time when a lot of work is happening, but there’s not much visual progress to see. As of today, the entire...
by hfdesigners | Jan 14, 2025 | Second Floor Addition
Month 1 Update We’re 4 weeks in and things are starting to take shape! All demolition is done, and framing is about 50% complete. Plumbers have started work inside. They’re rebuilding all existing plumbing and connecting it to the new bathroom upstairs. We...
by hfdesigners | Nov 4, 2024 | New Posts, Second Floor Addition
New Project: Rebuild and Second Story! This home on Eagle Mountain Lake had an interior fire that smoldered for hours. Everything in the home was water or smoke damaged. Faced with a large rebuild anyway, the client decided to add a second story to include an office...